Options
- A
Discretionary PMS
-
Non-Discretionary PMS
Correct answer
- C
Advisory PMS
- D
Passive PMS
Why this is the answer
In Non-Discretionary PMS, the manager provides recommendations, but the client’s approval is required before execution.